Case Study DFM DFA

Tractor Cooling Package DFA Optimization

How early stage Design for Assembly was used to simplify a tractor cooling package before industrialization, reducing part count and assembly effort while improving manufacturability and total package cost.

SectorAgricultural machinery
ServiceDFM DFA
FocusAssembly simplification
Representative tractor cooling package DFA concept image
ObjectiveReduce cooling package assembly complexity
MethodBoothroyd Dewhurst DFA and structured redesign
Baseline352 parts in the initial package
Outcome294 parts and 18 percent shorter assembly time
01 Engineering challenge

Assembly complexity was already embedded at concept stage

The cooling package was still in the early design phase, but the initial architecture had already grown to 352 parts. That created a high number of handling, fastening and insertion steps before the design had reached industrialization.

The engineering problem was therefore broader than simply cutting cost. The design needed fewer parts, fewer opportunities for assembly error and a cleaner route to production without removing components that were genuinely required for sealing, function or serviceability.

01
High part count

The baseline package contained 352 components before DFA actions were applied.

02
Assembly burden

Repeated fasteners, connectors and handling steps were extending assembly time and labour content.

03
Early design window

The work was carried out before industrialization, when geometry, interfaces and joining methods were still relatively inexpensive to change.

Baseline before concept of the tractor cooling package showing the original separate components and assembly interfaces
Baseline before concept used to frame the original assembly complexity and identify the separate components targeted during the DFA review.
02 Engineering approach

DFA levers turned the bill of materials into design actions

The review combined the bill of materials, CAD envelope data and the actual assembly sequence. Each component was screened for necessity, handling effort, insertion difficulty, securing method and potential integration with neighbouring parts.

01

Map

Import BOM and CAD information and understand how the package is actually assembled.

02

Question

Challenge part necessity, separate hardware, repeated connectors and avoidable handling.

03

Redesign

Use part commonization, multifunctionality, welding, standardization and better tool access.

04

Reassess

Recalculate part count, assembly time, DFA index and product cost after the changes.

10 DFA improvement pointswere identified across part elimination, material improvement, hardware reduction and assembly simplification.
03 Strategic design changes

The biggest gains came from combining functions and deleting hardware

Rather than chasing one dramatic redesign, the study accumulated value through a series of practical changes. Parts were combined where one component could perform several functions, brackets were removed when better access made them unnecessary, and welded features replaced avoidable hardware where appropriate.

Before and after examples of DFA improvements with the component geometry cropped clearly for comparison
Part commonization

One redesign combined three parts into a single functional part, removing two components and associated hardware.

Better tool access

A bracket could be eliminated after modifying the surrounding geometry so the fastener remained accessible during assembly.

Simpler joining

Selected hardware was removed by changing the joining strategy rather than adding more parts to solve the same problem.

04 Measured improvement

The redesigned packagebecame simpler to build

The final DFA reassessment confirmed fewer parts and fasteners, shorter assembly time and a higher DFA index. The total package cost reduction was smaller, but still meaningful for a high value component produced at volume.

Part count

Part count comparison before and after DFA redesign

Assembly time

Assembly process time comparison before and after DFA redesign

Total cost

Total cost comparison before and after DFA redesign
352 → 294parts, a reduction of about 16.5 percent
30fasteners removed from the assembly
18%shorter assembly process time
9.9 → 11.5DFA index, about 16 percent improvement
1.2%estimated total cooling package cost reduction
05 Key finding
Early DFA created value before assembly complexity became expensive to change

The strongest lesson was not the cost percentage on its own. Because the review happened during the initial design phase, the team could remove parts, change interfaces and alter joining methods before the package was locked into industrialization. That is where DFA has the greatest leverage.

06 Engineering outcome

A smaller BOM improved both assembly efficiency and design maturity

The revised cooling package used fewer components and less hardware while achieving a higher DFA index. Importantly, the redesign did not treat every part as a candidate for removal. Functional sealing elements and genuinely necessary interfaces were retained, while avoidable structure and assembly work were targeted instead.

Part reduction

Fifty eight parts were removed from the baseline package without changing its required function.

Assembly efficiency

Removing fasteners and simplifying handling reduced the assembly process by roughly one fifth.

Design quality

The higher DFA index reflected a more efficient product structure rather than a simple cost cutting exercise.

Commercial impact

The reported 1.2 percent package cost reduction is modest per unit, but material at production volume on a high value assembly.

Talk to an Engineer

Discuss Your DFM DFA Project

Share the product, assembly, available CAD and the cost or manufacturing problem. An engineer will review the starting point and confirm the most suitable DFM DFA, redesign or validation scope.

Engineering enquiryTell us what you need to engineer

The enquiry form is temporarily unavailable.